“Ford Farm Solar PV in St Ives in Cornwall. We were first approached in the first week of February 2013 and were contracted to deliver contestable connections of 33KV. We designed, installed and commissioned a 5MW solar PV installation for a 31 March energisation. That was a huge turnaround – we hand-built it within eight weeks. We were building it before the design was even accepted! Off the back of that, two weeks into the job, we got another job at Ashford in Taunton, Devon – and we delivered that for the 31 March too. Each was a ten-person job involving a lot of overtime, but we’re proud we delivered.”